published, includes proposals which would mean that all power generation schemes between 25MW and 50MW would be determined by Welsh ministers rather than local planning authorities (ie councils) as so-called Developments of National Significance (DNS).
The administration has made it clear that the current planning system is not supporting the delivery of renewable energy projects. It cited a Welsh Assembly report last year which said wind farm schemes were taking on average 122 weeks to be determined.